Aeolus Truck & Driver News
Vital court ruling for Mt Messenger project
Aeolus Truck & Driver News
An Environment Court ruling in early May clears the final remaining hurdle for the 6km Mt Messenger Bypass between the King Country and Taranaki.
The ruling supports the compulsory purchase of the final block of 11 hectares of land required for the project and dismisses the objection to the Public Works Act purchase of the land.
NZ Transport Agency Waka Kotahi has welcomed the ruling with General Manager Transport Services Brett Gliddon saying the ruling supports the approach and actions taken by NZTA and the Crown and follows a series of court rulings in favour of NZTA and the Crown over many years.
“This is the last parcel of land needed at the northern end of the Bypass,” Gliddon says.
...An Environment Court ruling in early May clears the final remaining hurdle for the 6km Mt Messenger Bypass between the King Country and Taranaki.
The ruling supports the compulsory purchase of the final block of 11 hectares of land required for the project and dismisses the objection to the Public Works Act purchase of the land.
NZ Transport Agency Waka Kotahi has welcomed the ruling with General Manager Transport Services Brett Gliddon saying the ruling supports the approach and actions taken by NZTA and the Crown and follows a series of court rulings in favour of NZTA and the Crown over many years.
“This is the last parcel of land needed at the northern end of the Bypass,” Gliddon says.
“It is always our preference to purchase property by agreement rather than compulsory acquisition. In good faith, and in compliance with the legislation, since 2017 we have made extensive efforts to acquire land by agreement.”
The bypass has faced complex challenges from the outset, with extensive delays caused mostly by multiple legal challenges – none of which have been successful.
“We acknowledge the cumulative impact this has had on the rate of progress and costs for the Bypass project. For example, a $37 million increase is the estimated impact of NZTA being unable to start work on the land in question during the 2023/2024 summer construction season alone,” Mr Gliddon says.
The Mt Messenger Alliance has made great progress in other areas of the new alignment, including 13% of earthworks completed and construction of the 235-metre tunnel about to commence, with strong support from project partners including Ngāti Tama as mana whenua.
“The Alliance team has worked tirelessly and innovatively to adjust their approach to construction while delays occurred,” says Mr Gliddon.
“For example, the project’s cableway to haul equipment and workers into the remote heart of the project area is a first for New Zealand and continues to receive accolades from within the industry.
“Once completed, the Bypass will provide much-needed interregional economic, resilience, safety and environmental benefits, including for local communities, businesses, freight and all State Highway 3 road users,” Mr Gliddon says.
The completed bypass will run for approximately 6km between Uruti and Ahititi and will include two bridges of approximately 125m and 30m in length as well as the 235m tunnel near the highest point of the new route.
It’s been a challenging legal road for the new bypass. Consultation began in 2016 and the selected route for the bypass was announced by then Transport Minister Simon Bridges in August 2017. At that time the project had a 2021 completion date but work did not begin until 2022. An estimated 4.5 year construction period suggests the bypass could open in 2027.